ಐಪಿಡಿಎಸ್ ಐಟಿ ಹಂತ-2

Ministry of Power, Govt. of India has launched Integrated Power Development Scheme (IPDS) IT enablement Phase –II for the urban areas having population more than 5000. RAPDRP Part-A will get subsumed in this scheme and continued as a separate component of IPDS.

 

44 Towns in HESCOM and total 124 towns across all ESCOMs in Karnataka are covered under this project.

 

Power Finance Corporation (PFC) is the nodal agency for IPDS IT Enablement.

 

The financial support by GoI to an extent of 60% of approved DPR cost i.e, Rs.10.22 crore convertible to grant (Max. 75% if the project is completed within timeline). No revenue expenditure considered in the DPR and need to be borne by Utility.

 

 


The project awarded during March-2020 in different packages as below:

 

Sl. No Package Firm Awarded Date
1 (a) DC-DRC Hardware and Software refresh across all ESCOMs of Karnataka M/s. Infinite Computer Solutions 26.03.2020
2 GIS survey M/s. Cyberswift Infotech Pvt. Ltd 30.03.2020
3 Fixing of Modems M/s Analogics Pvt. Ltd. 30.03.2020
4 IT Infrastructure M/s Idea Infinity Pvt. Ltd. 10.09.2020

 

 
Details of works under the project:

 

Replacement of Data Centre hardware procured under RAPDRP Part-A project and Implementation of 18 software application modules, covering both 98 RAPDRP towns and 124 IPDS towns across all ESCOMs.

 

Hosting Disaster Recovery Centre(DRC) on MEITY Empanelled Cloud.

 

GIS based Asset Mapping, Survey and Digitization and Integration of Consumer Indexing of all ESCOMs.

 

Supply and fixing Modems to Feeders/ DTCs/Boundary/HT installations in IPDS towns of all ESCOMs.

 

Supply and installation of IT infrastructure in the IPDS towns of all ESCOMs.

 


Stipulated Timeline by MoP/PFC:

 

DPR sanction 05.07.2017
Project Completion (24 months from DPR sanction) 04.07.2019
Project Verification and closure (30 months from DPR sanction) 04.01.2020
Project Completion (Extended) 31.12.2021
Project Verification and Closure (Extended) 31.03.2022

 

 

Progress so far:

 

Sl. No Package Physical Progress
1 DC-DRC Hardware and Software refresh across all ESCOMs of Karnataka and Hosting DRC on cloud Hardware:All necessary hardware viz., Servers, Switches, Load Balancer etc., supplied and installation under progress.
Software:Necessary software Licenses supplied
Application:AS-IS sessions for all modules completed and TO-BE documentation under finalization
2 GIS based Asset Mapping, Survey and Digitization and Integration of Consumer Indexing data GIS based Asset Mapping, Survey and Digitization and Integration of Consumer Indexing data is completed in all 44 IPDS towns.
3 Fixing of Modems Modems installed as per revised DWA quantity.
4 IT Infrastructure IT Hardware installed in all 44 IPDS towns.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

ಇತ್ತೀಚಿನ ನವೀಕರಣ​ : 17-07-2023 01:00 PM ಅನುಮೋದಕರು: Admin


ಹಕ್ಕುತ್ಯಾಗ

ಈ ಪುಟವು ಸರ್ಕಾರಿ ಸಚಿವಾಲಯ/ ಇಲಾಖೆ/ ಸಂಸ್ಥೆಗಳಿಗೂ ಲಿಂಕುಗಳನ್ನು ಕಲ್ಪಿಸುತ್ತದೆ ಎಂಬುದನ್ನು ದಯವಿಟ್ಟು ಗಮನಿಸಿ. ಈ ವೆಬ್ ಸೈಟುಗಳ ವಿಷಯಗಳು ಆಯಾ ಸಂಸ್ಥೆಗಳ ಸ್ವತ್ತೇ ಆಗಿದ್ದು, ಯಾವುದೇ ಹೆಚ್ಚಿನ ಮಾಹಿತಿ ಅಥವಾ ಸಲಹೆಗಾಗಿ ಅವರನ್ನೇ ಸಂಪರ್ಕಿಸುವುದು

ಜಾಲತಾಣ ನೀತಿಗಳು

  • ಹಕ್ಕುಸ್ವಾಮ್ಯ ನೀತಿ
  • ಬಾಹ್ಯಜಾಲತಾಣ ಸಂಪರ್ಕ ನೀತಿ
  • ಭದ್ರತಾ ನೀತಿ
  • ಕರಾರುಗಳು ಮತ್ತು ಷರತ್ತುಗಳು

ಸಂದರ್ಶಕರು

  • ಇತ್ತೀಚಿನ ನವೀಕರಣ​ :
  • ಸಂದರ್ಶಕರು :
  • ಆವೃತ್ತಿ :
ವಿಷಯದ ಮಾಲೀಕತ್ವ ಮತ್ತು ನಿರ್ವಹಣೆ : ಹುಬ್ಬಳ್ಳಿ ವಿದ್ಯುತ್ ಸರಬರಾಜು ಕಂಪನಿ ನಿಯಮಿತ
ವಿನ್ಯಾಸ, ಅಭಿವೃದ್ಧಿ ಮತ್ತು ಪ್ರಕಟಣೆ : ಇ-ಆಡಳಿತ ಕೇಂದ್ರ , ಕರ್ನಾಟಕ ಸರ್ಕಾರ © 2024, ಎಲ್ಲಾ ಹಕ್ಕುಗಳೂ ಕಾಯ್ದಿರಿಸಿವೆ

ಜಾಲತಾಣದ ಉತ್ತಮ ನೋಟಕ್ಕಾಗಿ ಕ್ರೋಮ್‌ v-87.0.4280.141, ಮೈಕ್ರೋಸಾಫ್ಟ್‌ ಎಡ್ಜ್‌ v-87.0.664.75, ಫೈರ್‌ಫಾಕ್ಸ್‌ v-83.0 ಬ್ರೌಸರ್‌ಗಳನ್ನು ಬಳಸಿ. ಸ್ಥಿರಚಿತ್ರಣ : 1280x800 to 1920x1080