IPDS IT PHASE-II

Ministry of Power, Govt. of India has launched Integrated Power Development Scheme (IPDS) IT enablement Phase –II for the urban areas having population more than 5000. RAPDRP Part-A will get subsumed in this scheme and continued as a separate component of IPDS.

 

44 Towns in HESCOM and total 124 towns across all ESCOMs in Karnataka are covered under this project.

 

Power Finance Corporation (PFC) is the nodal agency for IPDS IT Enablement.

 

The financial support by GoI to an extent of 60% of approved DPR cost i.e, Rs.10.22 crore convertible to grant (Max. 75% if the project is completed within timeline). No revenue expenditure considered in the DPR and need to be borne by Utility.

 

 


The project awarded during March-2020 in different packages as below:

 

Sl. NoPackageFirmAwarded Date
1(a) DC-DRC Hardware and Software refresh across all ESCOMs of KarnatakaM/s. Infinite Computer Solutions26.03.2020
2GIS surveyM/s. Cyberswift Infotech Pvt. Ltd30.03.2020
3Fixing of ModemsM/s Analogics Pvt. Ltd.30.03.2020
4IT InfrastructureM/s Idea Infinity Pvt. Ltd.10.09.2020

 

 
Details of works under the project:

 

Replacement of Data Centre hardware procured under RAPDRP Part-A project and Implementation of 18 software application modules, covering both 98 RAPDRP towns and 124 IPDS towns across all ESCOMs.

 

Hosting Disaster Recovery Centre(DRC) on MEITY Empanelled Cloud.

 

GIS based Asset Mapping, Survey and Digitization and Integration of Consumer Indexing of all ESCOMs.

 

Supply and fixing Modems to Feeders/ DTCs/Boundary/HT installations in IPDS towns of all ESCOMs.

 

Supply and installation of IT infrastructure in the IPDS towns of all ESCOMs.

 


Stipulated Timeline by MoP/PFC:

 

DPR sanction05.07.2017
Project Completion (24 months from DPR sanction)04.07.2019
Project Verification and closure (30 months from DPR sanction)04.01.2020
Project Completion (Extended)31.12.2021
Project Verification and Closure (Extended)31.03.2022

 

 

Progress so far:

 

Sl. NoPackagePhysical Progress
1DC-DRC Hardware and Software refresh across all ESCOMs of Karnataka and Hosting DRC on cloudHardware:All necessary hardware viz., Servers, Switches, Load Balancer etc., supplied and installation under progress.
Software:Necessary software Licenses supplied
Application:AS-IS sessions for all modules completed and TO-BE documentation under finalization
2GIS based Asset Mapping, Survey and Digitization and Integration of Consumer Indexing dataGIS based Asset Mapping, Survey and Digitization and Integration of Consumer Indexing data is completed in all 44 IPDS towns.
3Fixing of ModemsModems installed as per revised DWA quantity.
4IT InfrastructureIT Hardware installed in all 44 IPDS towns.